The Wisconsin Department of Transportation has scheduled the following maintenance activities in Lincoln, Marathon and Shawano counties for the week of Sept. 16:

Highway 29, Shawano County-wide

Sept. 18: Shawano County Highway Department will seal bridge end joints on Highway 29 throughout the county. Motorists will encounter mobile lane closures from 7 a.m. to 3 p.m., Sept. 18 through Sept. 20. Crews will continue that work on Sept. 23 through Sept. 27.

Sept. 16: WisDOT will complete soil borings on one bridge and roadway section on Highway 29 westbound at the Wolf River Bridge and Highway 22 interchange. The lane closures for westbound bridge over Wolf River and Roadway Section will begin at 7 a.m. through Sept. 17 at 3 p.m.

Sept. 17: Shawano County Highway Department will finish applying polymer overlays on two bridges, Highway 29 eastbound and westbound over Highway 55 and Highway 160. Work begins on Tuesday, 6 a.m. through Wednesday, 3 p.m.

Highway 52, Marathon County

Sept. 18: From 7 a.m. to 4 p.m., crews will remove and replace a culvert on Highway 52 east of the intersection at Mill Road in the town of Hogarty. Traffic will be detoured via Highway Y to Highway Z to Highway Q.

Highway 64, Lincoln County

Sept. 16-19: Lincoln County Highway Department will complete routine bridge maintenance on the Wisconsin River Bridge in the city of Merrill. Motorists will encounter a lane closure and temporary signals on Highway 64 at the bridge from 8 a.m. on Monday through Thursday at 4 p.m. Crews will continue this work during the week of Sept. 23.

Highway 107, Marathon County

On Sept. 16, from 7 a.m. to 4 p.m., crews will remove and replace a culvert north of Short Lane Drive, between Highway 29 and Little Chicago. Traffic will be detoured via Highway U, Highway O and Highway A.

Closures and maintenance activities are dependent upon favorable weather conditions and crew availability.