WisDOT bridge inspectors will be performing routine inspections next week in Marathon County. Motorists will encounter work zones at the following bridges:

  • WIS 153 bridge over the Big Eau Pleine River, west of Mosinee, will have a single lane closure on Monday, May 24, 9 a.m. to 3 p.m.
  • WIS 153 bridges over the Wisconsin River, Mosinee, will have single lane closures on Monday, May 24, 9 a.m. to 3 p.m.
  • Marathon County WW bridge over the Wisconsin River, village of Maine, will have a single lane closure on Tuesday, May 25, 8 a.m. to 3 p.m.
  • East Thomas Street bridge over the Wisconsin River, Wausau, will have a single lane closure on Tuesday, May 25, 8 a.m. to 3 p.m.
  • WIS 29 eastbound and westbound bridges over the Wisconsin River, Rothschild, will have single lane closures on Wednesday, May 26 from 8 a.m. to 2 p.m.

Crews will continue bridge surface repairs at the following location:

  • WIS 29 eastbound and westbound bridges over 72nd Avenue, 48th Avenue, and Little Rib River, Marathon county. Motorists will encounter single lane closures from Monday, May 24 at 7 a.m. through Friday, May 28 at noon.

Crews will also finish washing bridge decks in Lincoln county.

  • US 51 southbound over the Wisconsin River, Lincoln county, will have a single lane closure, Monday, May 24 and Tuesday, May 25, 6:30 a.m. to 5 p.m.

Some lane closures will require flagging operations. The inspection schedule is subject to change based on weather conditions.

For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s north central region:

Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.